21 We can roughly divide one release into two periods. The development period
22 and the freeze period. The former is 6 months long and the latter is about 2
25 During development period, contributors submit patches to be reviewed and
27 which is normally called the "cut-off date", after which the freeze period
32 During freeze period, the tree is closed for new features. Only bug fixes are
33 accepted. This period can be shorter or longer than 2 months. If it ends up
34 longer than 2 months, it eats into the next development period.
44 The Release Manager will not see much workload during development period, but
45 expects to see increasing workload during the freeze period until the final
51 period. The Committers will act on the wishes of the Release Manager during
58 their components in a timely manner, especially during the freeze period.
64 freeze period they transfer xen-unstable branch ownership and act on the
71 code they submitted during development period. Failing that, the Release
104 ## Development period
115 ## Freeze period
117 Before or at very early stage of the freeze period, agree with the Community